Шоссе I/38 Йиглава, окружная дорога

Jihlava

Construction type
Автодорожное строительство

Financial volume
CZK 614 million

Commencement Date
2002

Completion deadline
2004

Investor
Road and Motorway Directorate of the CR, Prague 4, Na Pankráci 546/56

Designer
Dopravoprojekt Brno, a. s., the project of the covered part was implemented by Amberg Engineering Brno company.

Suppliers
Consortium of companies: COLAS CZ, a. s. – vedoucí člen. Členové: Dopravní stavby Holding, a. s., Stavby silnic a železnic, a. s., OHL ŽS, a. s.

Load
 

The by-pass road is a significant transport construction both for the City of Jihlava, and for the Vysočina Region and its infrastructure. The by-pass route runs at a length of 1.9 km through the west part of the City of Jihlava and is connected to the existing I/38 four-lane road –  feeder road to the motorway from motorway D1 in the direction of Znojmo. The by-pass road is implemented as a longitudinally divided phase – the right half with the design speed of 80 km/h. The most significant part of the construction is the tunnel which is 304 m long and built by means of the “Milano Walls in an Open Cutting” technology. The tunnel has been designed as a double-tunnel structure, but only one tunnel tube was completed. The combined technology of mining and cutting-and-covering was applied in the tunnel construction. The other parts of the construction are anti-noise measures executed in the form of anti-noise walls and earth embankments, relocation of underground services (high-pressure, mean-pressure, and high-voltage cables). The tunnel construction also includes the complete technological equipment of the tunnel. Technical data: the total length of the construction is 1.9 km, the length of the tunnel is 304 m and in total the project includes 69 construction structures and 12 operational units.

 