Intensification and Reconstruction of the Sewage Treatment Plant and the Sewage Collection System in Jihlava

Jihlava

Construction type
Water-Management Construction

Financial volume
984 000 EUR

Commencement Date
2004

Completion deadline
2006

Investor
Svaz vodovodů a kanalizací Jihlavsko

Designer
HYDROPROJEKT CZ, a.s.

Suppliers
Sdružení firem ČOV Jihlava Členové: Metrostav a. s., OHL ŽS, a.s., SSŽ a.s., VCES a.s., IMOS Brno a.s.

 

The project comprised of three parts:

  1. Intensification and Reconstruction of the Sewage Treatment Plant in Jihlava,
  2. Connection of the sewage collection systems of the Antonínův Důl and Pávovo municipalities to the central sewerage system,
  3. Modernization and extension of the sewage collection system in Jihlava.

The sewage treatment plant in Jihlava was reconstructed and extended to the capacity of 99, 917 equivalent persons. The technology line of the plant was renovated so that treated sewage would meet the conditions set by the latest regulations, and the plant extension would secure a reserve capacity to cater for the further development of the city. The new technology uses the system of combined disposal of nitrogen and phosphorus (the R-AN-D-OAN system). The sludge generated is stabilized through an anaerobic process and then incinerated.

At the same time, the implemented project secured the complete sewage discharge from the remote municipalities of Antonínův Důl and Pávov by means of a separation system of sewage collection, with 1,650 households connected to it. The sewage from the location is carried away to the central sewage treatment plant in Jihlava.

The project also dealt with the renovation and increase in capacity of the most problematic sections of the unified sewage collection network in Jihlava and its extension to other locations. The B, BA, AA sewage collectors and the public sewer in Znojemská Street were reconstructed. New public sewers were constructed in the locations of Sasov, Hotov, Pístov and Helenín, enabling other 820 households to be connected.

In total, 24.682 m of new (gravitational and pressure) drain lines, nine pumping stations on the sewage collection network, one storm-water tank including a pumping station, and one cyclone separator were constructed under the project.

 